Knowing dimensions is handy for any rig design for sure. If you get actual meaurements I can check if it will fit in my design (using a corbeau sprint size s), or, can partially build the design from isr and see if it fits there. I wouldn't expect big issues though.
edit:
I have calculated pricing for JUST the profiles for my latest version of the rig design.
Code:
Profile 45x45L B-Type slot 10
Length: 6m: ( 2 x 1600 ; 4 x 600 ; 1 x 225 ; R:69 )
48,02 € 48,02 € Delete
Profile 45x90L B-Type slot 10
Maschining: - / -
Length: 700 mm
12,15 € 24,30 € Delete
Profile 45x45L B-Type slot 10
Length: 6m: ( 1 x 225 ; 9 x 500 ; 3 x 300 ; R:221 )
48,02 € 48,02 € Delete
Profile 45x45L B-Type slot 10
Length: 3m: ( 3 x 590 ; 3 x 300 ; R:232 )
24,01 € 24,01 € Delete
Profile 45x45L B-Type slot 10
Length: 500 mm
3,78 € 3,78 € Delete
plus MwSt. 19%: 28,14 €
Sub-total: 176,27 €
Motedis UG: Best Way: 15,00 €
This is just a quick calculation. However, I see room for improvement. I will investigate tomorrow how I can have this fabricated the most efficient way. Right now it probably isn't. For example, some of the remainder of material (the R values) are very close to the sizes of some parts. Hmmm.
So, I will set myself a challenge. By tomorrow evening I hope to have found the most cost and material efficient way of ordering the parts. I will also change the design to reflect this. This way there should be no guessing involved any longer when parts need ordering. I also will do a separate calculation for an even more budget friendly version by removing some parts from the rig. This isn't what I'd do personally, but I'm interested to see the savings which can be, if I'm correct, in the 30 to 50 euro range or over.
I think a new revision will be included as well to reflect the calculations for both, checked for errors this time
Really glad this design is taking on its final shape, and it is about time as well.
edit2:
another idea, I might reduce the total footprint of the rig even more, because I noticed a standard profile length pretty close to the length of my side rails, hmmm, opportunities... Also, my idea of removing some parts for a more budget option. I didn't calculate what you save on profile, but I did see what you can save concerning brackets, which is already almost 7 euro's, together with the profiles and t-nuts, you might be looking at a savings which essentially pay shipping costs